Informing the public about delays in completing large public projects

The reasons for delayed Jane Byrne Interchange project in Chicago are only now trickling out to the public:

In January 2015 — just over a year into construction — university workers noticed the building had been sinking and shifting, leaving cracks in the foundation and making it impossible to shut some doors and windows, according to court records…

Over the next 1½ years, IDOT blamed engineering firms it had hired for missing the poor soil conditions that contributed to the problem. That led to a redesign of a key retaining wall that boosted costs by $12.5 million and dragged out that part of the project at least 18 more months…

IDOT’s Tridgell gave the Tribune a list of other reasons for delays. Among them: The city was leery of shutting down ramps and lanes on many weekends because of festivals and other events. And other local agencies required extra permits and reviews for work…

UIC’s Sriraj said public outreach is challenging on big projects, with no “gold standard” on how much is appropriate.

The public is likely not surprised that such a large project is behind schedule and over budget. This is common on major infrastructure projects. They just want the project done. (And I’m sure some of the cynical ones will note that even when the Byrne project is done, repaving of its surfaces will probably begin again very soon.)

Is this expectation of poor performance what then allows public agencies to not have to explain further delays and costs? Realistically, there is little the public can do whether they know about the delays and cost overruns or not: the construction keeps going until it does not. And the article hints that there is possibly little the state can do to compel contractors to do better work. So, because the news looks bad, is it just better to sit on the information?

I would prefer it work this way: given that such large projects affect many people and involve a lot of taxpayer dollars, the public should have access to clear timelines and explanations for delays. Many people won’t care, not matter how much information is available. But, in general, public life is valuable and information should be widely available and not hidden for fear of angering people or avoiding blame. At the least, knowing about delays and increased costs could theoretically help voters make better choices in the future about leaders who will guide these processes.

2 thoughts on “Informing the public about delays in completing large public projects

  1. Pingback: Cost and time overruns on public projects do not matter once the task is done | Legally Sociable

  2. Pingback: Complicated urban repairs: 20 years to repair 11 blocks of Park Ave above and below ground | Legally Sociable

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s